Tuesday, October 13, 2009
Saturday, February 28, 2009
Sunday, August 24, 2008
Wiggins Pass dredging possibilities
The choices for future Wiggins Pass dredging projects have been narrowed down to three ideas.
This week, an engineering firm and Collier County committee decided to focus on the three ideas for future study. Coastal Planning and Engineering, in Boca Raton, is now working on those three ideas and plans to make a more detailed presentation in October.
The ideas being studied include:
• Getting rid of the natural S curve, by straightening the channel both inside and outside of the pass and by filling in the S curve with sand.
• Digging a straight channel inside the pass, but also leaving the natural S curve channel too.
• Keeping the natural S curve channel, but narrowing it from 250 feet wide to 150 to 200 feet wide and going to depth of 11 feet instead of 13 feet.
Collier County residents and officials say a new plan is needed because right now Wiggins Pass needs to be dredged every 15 months at a cost of about $750,000 per dredge.
Finding a solution for the rapid filling in of the pass is nothing new. Studies, ideas and lots of money have been invested to find a way to keep the pass open.
The 2004 study by Humiston and Moore stated that dredging exacerbated the erosion. That study recommended going back to an 8-foot deep dredge, dredging a flood shoal, making the channel shorter and straighter, doing nothing or adding groins. The 2004 study never got any further than being presented to the Coastal Advisory Council.
A $130,000, 2007 study by the engineering firm Humiston and Moore reported that the pass worked best before it was ever dredged. The study stated that the best solutions would be to return the pass to the way it was in the 1970s. Recommendations included: no action, reconstruct a shoal without structures, a jetty, t-groins, breakwater or a combination of breakwater and jetty. Each of those plans was then further studied.
One of the forerunners in 2007 was putting temporary t-groins by the pass to capture the sand and rebuild the shoals like there used to be naturally before dredging first began in 1984. The idea would be to remove the t-groins once the pass was stabilized.
"One of the leading things we are looking at are some type of structure," Coastal Projects Manager Gary McAlpin said in 2007 when the idea was being proposed. "I am in favor of temporary structures."
Now, he's changed his mind. This week McAlpin said he hopes to find an alternative that does not need structures in the pass.
"We are looking at doing something without structures," McAlpin said. "We can do it."
McAlpin said he does have a favorite yet among any of the three plans now being studied, by the Boca Raton firm, Coastal Planning and Engineering, and he doesn't want to comment on them until he has more information.
"We are not going to make any decisions until we look at these options," McAlpin said.
Donna Caron lives near Wiggins Pass and has been following plans for the waterway for years. She says it's hard to find a plan for such a dynamic environmental system as Wiggins Pass.
"The one the engineers like best is to take out the shoal in the inner channel and change the configuration of the outer channel. It will totally make everything straight in and out," Caron said.
"I believe that the theory is that if they take out that shoal and they put sand into the natural shoal, they think that the velocity that will happen by it going straight out will make the dredging period less. What they are trying to get to is a four or five year dredge cycle."
Caron said she'd like to see longer times between dredges.
"I live here by Wiggins Pass so I am very concerned about what happens here," she said. "My concerns are that the dredging that we have been doing is not working. It fills in faster and faster every time. We keep digging deeper and deeper and it keeps filling in faster and faster. We have not been looking at the environmental side of things. We've just been looking at getting bigger and bigger boats in and out. It needs to get back to as close to Mother Nature as we can get it."
In your voice
This week, an engineering firm and Collier County committee decided to focus on the three ideas for future study. Coastal Planning and Engineering, in Boca Raton, is now working on those three ideas and plans to make a more detailed presentation in October.
The ideas being studied include:
• Getting rid of the natural S curve, by straightening the channel both inside and outside of the pass and by filling in the S curve with sand.
• Digging a straight channel inside the pass, but also leaving the natural S curve channel too.
• Keeping the natural S curve channel, but narrowing it from 250 feet wide to 150 to 200 feet wide and going to depth of 11 feet instead of 13 feet.
Collier County residents and officials say a new plan is needed because right now Wiggins Pass needs to be dredged every 15 months at a cost of about $750,000 per dredge.
Finding a solution for the rapid filling in of the pass is nothing new. Studies, ideas and lots of money have been invested to find a way to keep the pass open.
The 2004 study by Humiston and Moore stated that dredging exacerbated the erosion. That study recommended going back to an 8-foot deep dredge, dredging a flood shoal, making the channel shorter and straighter, doing nothing or adding groins. The 2004 study never got any further than being presented to the Coastal Advisory Council.
A $130,000, 2007 study by the engineering firm Humiston and Moore reported that the pass worked best before it was ever dredged. The study stated that the best solutions would be to return the pass to the way it was in the 1970s. Recommendations included: no action, reconstruct a shoal without structures, a jetty, t-groins, breakwater or a combination of breakwater and jetty. Each of those plans was then further studied.
One of the forerunners in 2007 was putting temporary t-groins by the pass to capture the sand and rebuild the shoals like there used to be naturally before dredging first began in 1984. The idea would be to remove the t-groins once the pass was stabilized.
"One of the leading things we are looking at are some type of structure," Coastal Projects Manager Gary McAlpin said in 2007 when the idea was being proposed. "I am in favor of temporary structures."
Now, he's changed his mind. This week McAlpin said he hopes to find an alternative that does not need structures in the pass.
"We are looking at doing something without structures," McAlpin said. "We can do it."
McAlpin said he does have a favorite yet among any of the three plans now being studied, by the Boca Raton firm, Coastal Planning and Engineering, and he doesn't want to comment on them until he has more information.
"We are not going to make any decisions until we look at these options," McAlpin said.
Donna Caron lives near Wiggins Pass and has been following plans for the waterway for years. She says it's hard to find a plan for such a dynamic environmental system as Wiggins Pass.
"The one the engineers like best is to take out the shoal in the inner channel and change the configuration of the outer channel. It will totally make everything straight in and out," Caron said.
"I believe that the theory is that if they take out that shoal and they put sand into the natural shoal, they think that the velocity that will happen by it going straight out will make the dredging period less. What they are trying to get to is a four or five year dredge cycle."
Caron said she'd like to see longer times between dredges.
"I live here by Wiggins Pass so I am very concerned about what happens here," she said. "My concerns are that the dredging that we have been doing is not working. It fills in faster and faster every time. We keep digging deeper and deeper and it keeps filling in faster and faster. We have not been looking at the environmental side of things. We've just been looking at getting bigger and bigger boats in and out. It needs to get back to as close to Mother Nature as we can get it."
In your voice
Sunday, August 10, 2008
1969
Tuesday, July 8, 2008
Monday, September 10, 2007
Monday, August 13, 2007
Friday, August 10, 2007
Great view from the 1950s
Thursday, August 2, 2007
Tuesday, May 15, 2007
Monday, May 14, 2007
Birds eye view in 1997 looking west
Great pic from the mid 50's

Classic picture of a very rural Naples Park and Vanderbilt.On the upper left side you can see just the tip of Grand Canal Dr. Also notice the Cocohatchee River as it winds thru what is now Palm River before they dredged the Immokalee Rd. Canal. You can also see the railway and the bridge crossing over the river.Check out the north end of Vanderbilt where not all of the canals had yet to be finished
Monday, April 30, 2007
aerial photo from 1997
Thursday, March 22, 2007


Gulf Harbor is one of the original North Naples Florida neighborhoods developed in 1954 (which is OLD by Naples standards) by longtime resident John Pulling (think Airport-Pulling Rd). It was a 10 acre parcel carved out of the mangroves of the Cocohatchee River and Wiggins Pass and is still surrounded on 3 sides by mangroves. From it's small fishing village past with cozy winter cottages to present day year round water lover's paradise with new homes being built, Gulf Harbor is like no other neighborhood in North Naples.The purpose of this site is to preserve the history of the neighborhood for generations to come.These are a couple of old pics of Wiggins Pass marina back in the 60's.You can almost see Gulf Harbor in the upper right hand corner of 1st pic. I look forward to hearing stories from the oldtimers and hopefully getting into some of their old scrapbooks and photo albums. Please feel free to post your ideas.
Subscribe to:
Posts (Atom)











